Complete the Tanakpur-Bageshwar line and in-progress rail projects like Rishikesh-Karnaprayag on time
“Complete the Tanakpur Bageshwar rail line and other in-progress rail projects on the lines of Rishikesh-Karanprayag rail line in a time bound manner.”
KAAM CHALU HAIIn progressprovisional
The verdict
The Rishikesh-Karnaprayag line (central project, RVNL) reached 78% physical progress by Sep 2026, with completion now expected by Dec 2029, after the term. The document lists Tanakpur-Bageshwar as 'survey in progress' (p. 41); its status was not checked.
Rule applied: In progress: deadline not reached; rating is provisional and not counted in the final score
⏳ 169 din baakiImplied deadline (end of term): 23 Mar 2027Confidence: mediumAI draft · review pending
5/10prov.
Evidence timeline
- Manifesto9 Feb 2022· BJP UttarakhandcontextUttarakhand Drishti Patra 2022 (English), p. 6 ↗
“Complete the Tanakpur Bageshwar rail line and other in-progress rail projects on the lines of Rishikesh-Karanprayag rail line in a time bound manner.”
- News15 Sept 2026· Indian InfrastructuresupportsRVNL achieves final breakthrough of escape tunnel-1 under Rishikesh-Karanprayag New Rail Line Project in Uttarakhand ↗
“Overall physical progress of 78 per cent with tunnel excavation 97 per cent; construction expected to be completed by December 2029.”
Promise ID bjp-uk-2022-033 · drafted 5 Oct 2026 by research-agent · JSON